New hangar taxi lane project

In case you didn’t get the memo…

Hi all,

PNW is going to resume work on the new hangar taxi lane project starting next Monday 8/21/23. Work will include the following impacts to Taxiway B and G.

  • Tuesday 8/22/23 and Wednesday 8/23/23 - Daytime closures of Taxiway B south of Taxiway F for storm pipe installation.
  • Thursday 8/24/23
    • Noon to 6 pm – Closure of Taxiway B south of Taxiway F for storm pipe installation.
    • Half day closure of Taxiway G north of Taxiway F for pavement sawcutting.
  • Monday 8/28/23 and Tuesday 8/29/23
    • Daytime closure of Taxiway B and G north and south of Taxiway F for storm pipe installation.
  • Thursday 8/31/23
    • Daytime closure of Taxiway B and G north and south of Taxiway F for trench patch paving.