In case you didn’t get the memo…
Hi all,
PNW is going to resume work on the new hangar taxi lane project starting next Monday 8/21/23. Work will include the following impacts to Taxiway B and G.
- Tuesday 8/22/23 and Wednesday 8/23/23 - Daytime closures of Taxiway B south of Taxiway F for storm pipe installation.
- Thursday 8/24/23
- Noon to 6 pm – Closure of Taxiway B south of Taxiway F for storm pipe installation.
- Half day closure of Taxiway G north of Taxiway F for pavement sawcutting.
- Monday 8/28/23 and Tuesday 8/29/23
- Daytime closure of Taxiway B and G north and south of Taxiway F for storm pipe installation.
- Thursday 8/31/23
- Daytime closure of Taxiway B and G north and south of Taxiway F for trench patch paving.